Late orders: the 5 most common production planning mistakes

4 min read

By the time a delay is noticed, it is too late: the customer has called, the shipment has been missed. Most late orders are not caused by a lazy workshop but by a few recurring planning mistakes. Here are the five most common.

1. Promising dates without seeing capacity

When sales takes an order, it does not know how loaded the workshop is over the coming weeks. The date given is well-meant but not realistic.

Solution: Check work-centre load before promising a date. Capacity planning shows when a new order can really be finished.

2. Seeing material needs too late

Just as production is about to start, a material turns out to be missing. Purchasing places an urgent order and the job waits for the lead time.

Solution: Calculate material requirements from the BOM as soon as the order arrives. The stock and requirements report shows shortages before production; purchase requests are raised on time.

3. Planning without tracking the actual

A weekly plan is made, but which job has fallen behind only becomes clear at the end of the week. By then the delay has piled up.

Solution: Track plan and actual side by side, live. Records from production terminals and the live production dashboard show a late work order the same day.

4. Losing track of subcontracted work

A part is sent out for painting or coating with the thought "they will tell us when it is ready". The subcontractor's delay is noticed on assembly day.

Solution: Track subcontracted work like a work order: when did the material go, when is it due back, is there a partial delivery? Every status should be visible in the system.

5. Leaving shipping to the last day

Production finishes, but packing, paperwork and transport are arranged on the last day. One small hitch pushes the whole shipment to the next day.

Solution: Plan shipping together with production. Shipment tracking with delay alerts flags orders that are nearly due but not ready.

Meeting deadlines is less about working harder than about seeing earlier. When capacity, material, production, subcontracting and shipping are connected in one system, a delay is noticed before the customer calls.